Against the backdrop of a rapidly shifting global economy moving towards sustainable production models and supply chain optimization, the Wooden Stories Manufacturing Factory project emerges as a shining beacon of modern industrial architecture. Positioned as a premier manufacturing hub for high-end wooden furniture and interior products utilizing a closed-loop system, the factory demands the most stringent engineering and construction standards from its foundations up to the superstructure. The selection of structural steel solutions for the entire flooring and workshop framing system not only optimizes usable space and delivers superior load-bearing capacity but also significantly compresses the overall construction timeline of the entire project.
Moving into Phase 2 of the infrastructure development campaign, the steel floor installation item plays a pivotal role, directly dictating the subsequent installation schedule for high-tech machinery and advanced technological assembly lines. This specific zone will endure immense dynamic and static loads throughout the lifecycle of the factory's manufacturing operations. Fully recognizing this strategic importance, the Site Management Board, along with the entire team of engineers and technical workers, has focused intensively on deploying the most advanced construction technology solutions to bring this section to the finish line on schedule, fulfilling solid quality commitments made to the Investor.
On May 27, 2026, the atmosphere at the Wooden Stories Manufacturing Factory construction site was exceptionally urgent, dynamic, and professional. Under the direct leadership and strict supervision of Chief Supervisor Pham Hoang Son, all human resources and equipment were fully mobilized to execute highly complex engineering tasks. According to the latest official site log, the completed volume of the Phase 2 steel floor installation has officially hit the 91% milestone. This impressive figure stands as a powerful testament to excellent project management capabilities and the tireless work ethic of the collective staff on site.
| Information Category | Site Data Details (Updated May 27, 2026) |
|---|---|
| Project / Construction Name | Wooden Stories Manufacturing Factory |
| Core Construction Item | Steel Floor Installation Phase 2 |
| Responsible Supervising Engineer | Pham Hoang Son |
| Completed Work Volume | 91% (Finishing and technical inspection stage) |
| Handover Progress Status | To Be Updated (Expected to exceed the original schedule) |
| Direct Workforce Mobilized | 1 Technical Supervisor + 4 High-grade Mechanical Workers (Elite Team) |
| Equipment & Machinery Utilized | Alloy disc cutting machines, high-current industrial welding machines, concrete core drills |
Regarding the expected handover timeline, the Site Management Board is currently coordinating closely with the Investor's supervising consultants to conduct step-by-step partial handovers (sequential handovers). The "To Be Updated" status on the progress management system serves as a calculated buffer zone to optimize load testing procedures, ultrasonic weld testing, and geometric elevation calibration. This thorough preparation ensures that the moment the official handover is announced, the steel floor plane will be in an absolute flawless state, ready for subsequent architectural finishing works without any technical interface conflicts.
To achieve the remarkable 91% volume milestone within a compressed timeframe while unconditionally adhering to strict technical standards, the Site Management split the layout into independent, mutually supportive construction fronts. Two core technical tasks implemented concurrently include:
The fabrication and positioning of steel floor plates represents a complex sequence demanding extreme geometric precision. Prior to being hoisted to their final structural positions, all steel floor plates undergo rigorous elevation checks, geometric dimension verifications, and surface flatness tests at the low-pressure pre-fabrication yard. Once the steel plates are precisely aligned onto the secondary beam network using specialized industrial jigs, high-grade mechanical welders initiate the permanent structural joint welding.
The structural welding for the steel floor components at the Wooden Stories project utilizes advanced manual arc welding coupled with semi-automatic gas metal arc welding (GMAW). This combination guarantees deep penetration, eliminating slag inclusion and porosity within the weld bead. Engineer Pham Hoang Son directly uses specialized weld gauges and ultrasonic non-destructive testing (NDT) equipment to randomly inspect every single welded segment. This meticulous precision ensures that each welded joint functions not merely as a simple mechanical connection but as a continuous load-bearing link, highly resistant to material fatigue and localized vibrations when the factory enters mass production.
While the steel floor plate network determines the surface flatness and direct load-bearing capacity, the process of chemical anchoring for the structural beam bolts into the reinforced concrete columns serves as the ultimate key to guaranteeing the structural stability of the entire composite system. This represents a critical interface transition link connecting the existing concrete structure to the newly added load-bearing structural steel framing system of Phase 2. The entire procedure is executed with extreme discipline via state-of-the-art chemical anchoring technology.
First, technicians utilize diamond core drills to precisely locate and drill holes into the concrete columns according to the structural engineering blueprints, ensuring zero damage or cutting into the primary internal steel rebar reinforcement of the columns. After the pre-drilled holes are thoroughly cleaned of all residual concrete dust using high-pressure air compressors and specialized wire brushes, imported high-strength structural anchoring adhesive is injected in precisely calculated dosages. The high-strength threaded bolts are then driven into the hole using a continuous spiral motion to ensure the chemical compound completely fills all microscopic voids. The entire structural steel beam network is only allowed to be connected and tensioned to its designed engineering torque values after the chemical adhesive has achieved its fully mandated curing duration. This method creates a rigid, enduring structural connection capable of withstanding immense shear and tension forces.
One of the primary hallmarks confirming the status of a Class-A industrial contractor is the capability to masterfully optimize construction resources. For the Phase 2 steel floor installation at the Wooden Stories factory, the organizational chart at the site front consists of only 1 specialized technical supervisor and 4 highly skilled mechanical workers. To an outside observer, this may appear to be a minimalist crew, but the actual on-site productivity delivered has proven a highly scientific philosophy of labor management.
Instead of flooding the site layout with a large volume of unskilled laborers—which causes physical interference, clutters work fronts, and complicates safety management—the contractor implemented the formula of "Elite Human Resources + Synchronized Technology". All 4 workers deployed on site are high-ranking mechanical technicians with the independent ability to interpret intricate engineering blueprints and fully master complex technological equipment. Their coordination achieves a state of seamless harmony—one worker handles positioning, two manage tack and structural welding, and one conducts surface preparation—forming an uninterrupted production line right on the active construction floor.
Providing robust backing to this elite workforce is a synchronized array of carefully curated construction machinery:
Next-Generation Alloy Disc Cutters: Enabling rapid, clean cuts through thick steel floor plates, leaving sharp, unwarped edges free from thermal deformation, thereby eliminating mechanical grinding overhead.
High-Current Industrial Welding Inverters: Guaranteeing a perfectly stable welding current even amidst site power supply fluctuations, ensuring a uniform arc and producing weld beads of flawless aesthetic and technical quality.
High-Power Core Drills and Dynamic Impact Drills: Ensuring that the drilling and anchoring of structural bolts into high-grade concrete elements proceed rapidly, with millimeter-level accuracy, without inducing micro-fractures or damaging surrounding concrete structures.
Within the operational framework of any construction team, the caliber of the technical manager dictates 50% of the overall success of the engineering item. Engineer Pham Hoang Son, possessing extensive tenure and a rich track record in heavy industrial steel structure construction, has excellently fulfilled the role of an on-site conductor at the Wooden Stories project. Moving far beyond the passive paradigm of inspecting technical parameters after work completion, he aggressively enforces the methodology of "Proactive Supervision and Early Risk Mitigation".
Prior to every single work shift, Engineer Pham Hoang Son conducts a mandatory Pre-Task Safety Meeting (Toolbox Meeting) with the crew, breaking down explicit work targets and outlining strict preventative measures against falls from heights, electrical shock hazards, and fire prevention during hot work operations. Throughout the execution cycle, he is continuously present at critical structural nexuses to verify the alignment of the beam systems, floor elevation accuracy, and most importantly, the adhesion integrity of the chemical bolt anchoring. His uncompromising strictness in internal quality assurance creates a supreme quality filter, resulting in consecutive flawless handovers to the Investor's independent consultants with zero re-work required.
At a certified Class-A construction site, occupational health and safety is never a superficial slogan—it is an absolute corporate culture. The Phase 2 steel floor installation demands that workers operate at elevated heights and maintain continuous exposure to high-thermal energy sources from welding and cutting gear. Consequently, comprehensive protective countermeasures, such as the assembly of secure temporary scaffolding, heavy-duty anti-fall safety netting systems, full-body safety harnesses connected to permanent lifelines, and localized portable fire extinguishers at every hot work station, are fully deployed and rigorously audited every single day.
With the completed work volume proudly standing at 91%, the journey to the final destination of the steel floor installation at the Wooden Stories Manufacturing Factory project is within arm's reach. The seamless integration of premium supervisory leadership from Engineer Pham Hoang Son, the elite craftsmanship of the mechanical crew, and a synchronized tech array has forged an industrial asset that is not only structurally invincible but also a masterpiece of industrial aesthetics. This will undoubtedly serve as a rock-solid foundation for the successful operational launch of the Wooden Stories factory, generating massive economic value for the Investor and cementing the contractor's dominant leadership position in the Vietnamese industrial construction market.
CHUAN'A CONSTRUCTION INVESTMENT JOINT STOCK COMPANY