Project Information:
Project: ... COMPANY
Category: Foundation Base Construction (Rebar installation, formwork, and preparation).
Supervisor: Bui Chi Hung.
Specific Tasks for the Day:
Inspected and finalized the foundation reinforcement (rebar) system.
Reinforced the formwork system to ensure tightness and alignment with the axes.
Cleared and cleaned the site post-construction for inspection readiness.
Manpower & Equipment:
Manpower: 01 Technical Supervisor + 04 Skilled Workers.
Equipment: Total station/leveling machine, steel cutter, welding machine, and specialized hand tools.
Implementation Progress:
Completion Rate: 98%.
Evaluation: Work is strictly following the schedule; quality meets technical standards.
Plan: Complete the remaining 2% and conduct inspection in the next shift.